The final report on the implementation of the city’s comprehensive program for the preservation and development of the historic center of Odessa for 2019-2021 was to be approved by the deputies of the city council at today’s session.
This project was put to a vote in a single block with other reports, but it did not receive the required number of votes, reports the correspondent of “Dumska”.
The day before, the report was discussed at a meeting of the specialized commission of the assembly.
According to the recently appointed head of the department for the protection of cultural heritage objects, Fedor Stoyanov, the main goal of the program is the restoration of monuments, which includes the preparation of the necessary documentation, project development, obtaining permits from the regional administration and the State Architectural and Building Inspection, as well as the actual work 638 million hryvnias out of 651 million hryvnias planned in the budget were spent on all this in three years.
“Not all plans were implemented, funding did not come in full, there was a quarantine and a pandemic,” said the chief guardian of cultural heritage. — Sometimes project work and obtaining permits took a whole year. The lion’s share of the funds went to the Department of Capital Construction, which carries out the main part of the works.”
According to the official, the integrated approach was a good idea from the beginning, but some departments could not work at the required level.
In turn, Boris Panov, the head of the capital construction department, answering the questions of the deputies about the low pace of work – eight facades per year, complained about the lack of professional personnel and their outflow abroad. In addition, many contractors terminated their contracts due to the war.
“Six objects are currently in operation,” Panov said. – They moved to a new program. Including the Liebman House, there remains to finish the tower and some restoration work. We will finish it this year. In addition, the development of scientific and project documentation for 67 objects is underway. Work has not yet started on 116 objects, but most of them have also been included in the new profile program.”
In total, 23 of the 212 planned objects were repaired.
At the end of the discussion, the deputies expressed their displeasure that the report according to the old program takes place a day before the adoption of the new program by the deputies’ corps, without actually working on errors.
“On April 5, the executive committee adopted a new program for the following years,” noted deputy Eduard Stas. — As a specialized commission, we did not expect to be accepted without discussion and familiarization, without consulting with us. It turned out the other way around — first they accepted the new program, and we are only now listening to the report on the old one. They adopted a new program without us, and the second point was that control over implementation rests with us.”