The Kyiv city military administration did not abandon the projects that were planned before the war. Work on the construction of the subway  on Vynogradar in Kyiv will be continued, but the administration did not name the exact dates.

This was  stated  by the First Deputy Head of the Kyiv City State Administration, Mykola Povoroznyk, reports the  National Industrial Portal  with reference to Suspilne .

The capital will also continue to upgrade infrastructure, such as bridges, transport interchanges, schools, kindergartens, parks and hospitals. According to him, such facilities cannot wait for the end of the war to resume operations.

“They need to be maintained in proper condition so that it does not lead to destruction. For example, underground tunnels are dug up, they can simply collapse,” said the deputy head of the KMDA.

Many Kyivites are asking to open other exits at metro stations, which have been closed since the beginning of the Russian invasion. Povoroznyk explained that the KMVA received such security measures from law enforcement officers and the military. Decisions will be changed only when permission is received.

Problems with the construction of the subway in Vynogradar

According to Deputy Mayor Volodymyr Bondarenko, in 2018 an agreement was signed between KP “Kyivskyi metropoliten” and JSC “Kyivmetrobud” on the construction of the section of the Syretsko-Pecherska subway line from the “Syrets” station to the Vynogradar residential area from the electric depot in the Podilsky district. Financing was carried out from the budget funds of Kyiv.

Photo: PJSC “Kyivmetrobud”

However, in November 2022, the commercial court of Kyiv collected more than 129 million hryvnias from JSC “Kyivmetrobud” in favor of the territorial community of the city for non-fulfillment of the terms of the contract

In February 2020, the SBU exposed the mechanism of seizing budget funds allocated for the construction of the subway in the Vynogradar housing estate in Kyiv.

blank

In November 2021, the Kyiv Prosecutor’s Office reported that it wanted to collect 183 million hryvnias from the contractor for the construction of the subway on Vynogradar “Kyivmetrobud” due to the fact that the company used the money for the wrong purpose, having deposited 1.5 billion hryvnias.

Later it became known that the Pechersk District Court of Kyiv seized the bank accounts of “Kyivmetrobud” as part of criminal proceedings to prevent the fraudulent appropriation of budget funds by officials of this PJSC and controlled enterprises during the construction of the Vynogradar metro.

blank

The cost of the construction of the two stations is about UAH 6 billion, of which the city allocated UAH 4 billion. It is planned that the two new stations will carry more than 90,000 passengers per day. The length of the metro section for the two new stations is 3.7 kilometers.