19 November 2026

@Hinshtein / Telegram
Since the start of the war, the authorities have been unable to complete over 290 federal state construction projects totaling 9.5 trillion rubles, according to The Moscow Times, which analyzed federal agency registries. Another 380 planned projects, worth at least 1 trillion rubles, have not even begun. These include new roads, bridges, children’s hospitals and cancer centers, wastewater treatment facilities, research laboratories, and industrial facilities. In most cases, the authorities cite a lack of funding as the reason for the postponements, while less frequently, the lack of necessary equipment.
In 2021, 15 construction projects had their completion dates pushed back, with 24 delays in 2022, 26 in 2023, 59 in 2024, 86 in 2025, and 81 in 2026. Some projects have been postponed multiple times: for example, the construction of the Supreme Court of the Russian Federation judicial quarter in St. Petersburg and the Nanotechnology Laboratory of the Kurchatov Institute National Research Center were postponed four times. But even the number of projects postponed for the first time is growing year after year.
“To officially admit a freeze is to admit failure. And admitting failure in today’s Russia is not good, it’s not helpful, you’ll be punished for it. So, no one’s saying we’re mothballing construction—we’re pushing it back. This expression, ‘shifting to the right,’ is about as ingenious, a wartime newspeak, as negative growth.”
Igor Lipsitseconomist
As one senator familiar with the situation in the construction industry explained to The Moscow Times, the freezing of projects, even after the collapse, accompanied all major crises in Russia and was the first sign of serious problems in the economy.
“Optimizing capital construction is a common practice, used during the 1998 default, the 2008-2009 global financial crisis, the 2020 crisis, and the onset of the pandemic. Today, we face equally significant challenges. The government has a proven plan of action, and it will be guided by it,” the source said.
How they counted
In its calculations, The Moscow Times analyzed information from the register of capital construction projects, as well as project passports for federal programs such as “Transport System Development,” “Education Development,” “Scientific and Technological Development of the Russian Federation,” and “Education Development.” Officially, not a single project has been cancelled or frozen, but completion dates are constantly being pushed back. The calculations only included projects for which construction had already begun but was delayed or suspended.
The most expensive project, with multiple delays, is the Ust-Luga Gas Processing Complex (3.5 trillion rubles). The first stage was planned for launch in 2023, the second by the end of 2024. In November 2020, Gazprom pushed back these deadlines by a year. In 2024, the dates were adjusted again in the new project passport. The launch of the gas processing and gas chemical complexes is now planned for 2026–2027, and the LNG plant for 2027–2028.
The second most expensive project, the Northern Latitudinal Passage, with a total cost of 850 billion rubles, is a railway line over 700 kilometers long that is intended to connect the Yamalo-Nenets Autonomous Okrug and the Ural railway line. It is needed both by oil and gas companies for exporting their products and by residents of northern cities. Construction of the Northern Latitudinal Passage began in 2011 and was repeatedly delayed. As a result, the latest version of federal programs postponed the opening of the Northern Latitudinal Passage to 2031.
The Kursk NPP-2 completion date (508.7 billion rubles) was also postponed. Construction began in 2016, with the opening planned for 2022. Since then, the planned completion date for the two reactors has been postponed four times. As a result, the first power unit was launched in 2026, and the second is now scheduled for 2028.

Problems arose with the nuclear icebreaker Rossiya (199.6 billion rubles) with two RITM-400 reactors: it was supposed to be launched in 2027, but in 2024, First Deputy Prime Minister Denis Manturov set a new target—2030.
Rounding out the top five most expensive long-term construction projects is the Lena River bridge, costing 174.8 billion rubles. It is designed to provide year-round connectivity between Yakutsk and the Lena, Kolyma, and Vilyuy federal highways. The Yakutia bridge is almost 50 billion rubles cheaper than the Crimean Bridge, but the Crimean Bridge was built in two years, while the Yakutia bridge has been promised since 2006 and has been delayed eight times.

Without roads, hospitals and housing and communal services
Transport accessibility projects were the most frequently frozen: a total of 128 state-owned construction projects, worth over 3.4 trillion rubles, were postponed. These included the Southern Bypass of Saratov, the Northern Bypass of Omsk, the Novorossiysk Transport Hub Development, and the Murmansk Transport Hub (Vykhodnoy-Lavna railway line).
The opening of the Krasnoyarsk metrotram has been postponed from 2026 to 2029 due to an increase in construction costs from 89 to 122.9 billion rubles.
“Citizens really want the metrotram. It will provide travel from one bank of the city to the other, bypassing traffic jams,” a Krasnoyarsk official lamented in an interview with The Moscow Times. “2028 marks Krasnoyarsk’s 400th anniversary. That means we have to get it running, no matter what. It’s a matter of principle, otherwise everyone in the local government will look like idiots.”
official of the Krasnoyarsk city administration
The opening of the Putilovskaya-Karetnaya metro section in St. Petersburg has been postponed from 2029 to 2030.
“Metro construction in St. Petersburg has long been the stuff of jokes. No one believes this or that station will open on time. Yes, this section is highly anticipated by people living in new buildings near the bay. Although there are more serious problems there now: the port is being bombed nearby,” one of the city’s municipal deputies told The Moscow Times.
Healthcare facilities are in second place: during the war, 43 hospitals and clinics, including oncology clinics, were delayed in their completion dates, costing a total of 438.5 billion rubles. These include new treatment and diagnostic buildings at the Stavropol Regional Oncology Center, the Sevastopol Oncology Center, and the Oncology Center in Nalchik.
Cancer patients in Stavropol complain that they can’t get an appointment for up to a month and a half. A Svetlogorsk resident told a local publication that her father, who had stage four cancer, received an appointment only after six weeks, but died without ever seeing one. And a Budyonnovsk resident, after a long wait for help, was only able to receive pain medication on the day of her death.

In 2022, residents of Kabardino-Balkaria recorded a collective appeal to Putin and Bastrykin demanding an inspection of the local cancer center. Among other violations, they cited huge queues for appointments and CT scans. According to those who appealed, many do not survive long enough to receive treatment.
Six children’s medical institutions also failed to complete their work on time: the Federal Children’s Rehabilitation Center in Yevpatoriya, the Regional Children’s Hospital in Kursk, the Regional Children’s Hospital in Chita, the Republican Children’s Hospital in Tyva, the Tver Regional Children’s Clinical Hospital, and the surgical wing of the Chelyabinsk Regional Children’s Clinical Hospital.
Since the start of the war, the share of healthcare in the country’s budget has been shrinking. Funding for programs within the national “Health” project has been cut separately. For example, state funding for cancer treatment has fallen by as much as 70%, and spending on modernizing primary healthcare and combating cardiovascular disease has been slashed.
The third-largest number of long-term construction projects is represented by 11 housing and utilities projects, such as “Stage II of the Water Supply Route from the North Crimean Canal to Feodosia and Kerch.” The project was created to address water shortages in the eastern part of the peninsula, which affects over 400,000 people. According to initial plans, the work was supposed to be completed in 2020. However, the commissioning of the project was delayed for nine years.
The launch of the Yevpatoria sewage treatment plant has been postponed from 2024 to 2028, and the completion of the modernization of the resort town’s water supply and wastewater networks has been pushed back from 2026 to 2029. The sewage treatment plant at Cape Ilya in Feodosia is expected to be launched with a four-year delay.
Furthermore, the launch of new wastewater treatment facilities in Ingushetia, Ulyanovsk, Nizhny Tagil, Ulan-Ude, and the Leningrad Region is being delayed. Local water utilities have been repeatedly convicted and punished for discharging untreated sewage into rivers. In Sunzha, residents signed collective complaints against the discharge of wastewater into the river. In Nizhny Tagil, local residents filed complaints with the prosecutor’s office and the Investigative Committee regarding the discharge of sewage into the river. Investigative Committee head Bastrykin intervened and promised to investigate, but nothing changed.
The completion dates for cultural centers and complexes have also been postponed, and construction of scientific laboratories, agricultural projects, and other projects has not been completed.
The number of long-term construction projects may increase sharply
In June of this year, the Ministry of Construction published a letter recommending postponing the implementation of projects for which construction had not yet begun, so that the freed-up funds could be used to complete those already underway.
A correspondent for The Moscow Times discovered 382 projects in the capital construction register that have not yet begun. Among the most expensive are the Yegoryevskoye Highway alternate, Lyubertsy-Kosherovo (115.4 billion rubles), the cargo terminal on Cape Nagleinyn (42.9 billion rubles), and the MegaScience facility on Russky Island (39.6 billion rubles). Most of the projects have no price list; the total cost of those that were quantified exceeds one trillion rubles.
Among the unfinished projects are 47 educational ones (for example, the Interuniversity Campus “Baikal” in Ulan-Ude and the educational center of the Russian Ministry of Foreign Affairs “Kalchuga-2” in the Moscow region), 34 medical centers (including the complex of buildings of the Kostroma Psychiatric Hospital and the Moscow Center for Medical Innovation and Bioengineering of the B.V. Petrovsky Russian Scientific Center of Surgery).
A total of 1,238 capital construction projects were listed in the register of capital construction projects and departmental programs during the war years. Of these, 294 are being postponed and 382 are highly unlikely to be started. 402 projects have been completed, and another 160 are still on schedule. The total cost of these projects, whose completion is postponed or cancelled, exceeds 10.5 trillion rubles—enough to pay pensions for a year. The Kremlin spends the same amount on military operations for six months.
“When budgetary funds are tight, postponing some new construction projects and using the money to complete those already underway is common practice. Postponing the start of construction is easier than cutting pensions, salaries, or payments under existing contracts,” says economist Nikolai Kulbaka.
Economists compare the situation to the late Soviet period, when construction plans were systematically disrupted: according to the USSR State Statistics Committee, from 1986 to 1988, approximately a third of critical economic projects were not completed on time each year, and by 1989, the figure had fallen to one in two. And in 1989, the Council of Ministers even ordered the mothballing of long-term construction projects due to funding cuts.
“Russia is once again following the Soviet Union’s path. It’s so recognizable, it’s unfinished business, a constant in the Soviet economic lexicon. Everyone would budget for construction with the small sums they could squeeze out of their superiors, but there wasn’t enough money to build it, but the foundation pit was dug, and then construction was put on hold under the pretext that the money would eventually become available.”
Igor Lipsitseconomist
Economist Dmitry Nekrasov also sees similar trends, but notes that the volume of disrupted construction is significantly lower than during the perestroika period. He calls the freeze on projects a logical adjustment, while the volume of construction in the first years of the war was unprecedented.
“The increase in construction volumes in 2022–2025 seems abnormal, rather than the current decline. Moscow has opened 27 new stations and 64 kilometers of new metro lines, and 74 stations and 171 kilometers of new above-ground lines. This is a third of Berlin’s entire existing U-Bahn and S-Bahn, respectively. The completed underground section is longer than Kyiv’s entire existing metro.”

“Another 380 planned projects, worth at least 1 trillion rubles, have not even begun. These include new roads, bridges, children’s hospitals and cancer centers, wastewater treatment facilities, research laboratories, and industrial facilities.”
The cockroaches don’t need roads, bridges, children’s hospitals, cancer centers, wastewater treatment facilities, research laboratories, or industrial facilities. They need war.
Mafia land has always been a shithole and the mass-murdering vampire has made sure it’ll stay that way for decades to come.
Orange BLOB Nazi Trump Organization Will Finance The Construction Of Russia At A Price FREE OIL Gas , Diesel
There is no free lunch, the Orange BLOB Nazi Trump will eat it.
We’ll see about that. Come January, Taco is facing a new Congress.